Stewardship scorecard · updated August 21, 2026

The META Campus

Meta currently rates 7.5 out of 10 on our stewardship scale.

It could be a 10. At this scale, it should be.

A CA$13-billion, gigawatt-scale project has the resources to deal properly with noise, water, power, emissions, infrastructure and eventual cleanup. None of those are unsolvable problems. The remaining points should be earned with design, binding commitments and measured results, not promises.

Start with the answer

Why 7.5 out of 10?

This is our public-record assessment, not a regulatory ruling. A point can move as permits, contracts, designs and operating data become public.

1.0

Siting & land use

The campus is in Alberta's Industrial Heartland, an established heavy-industrial area rather than a residential neighbourhood.

Strong
1.0

Data-centre cooling

Meta says the data centre will use closed-loop liquid cooling with dry heat rejection and no operational cooling-water use.

Strong
1.0

Power supply plan

The supply chain is unusually visible: AESO connection allocation, Capital Power interim supply and dedicated Greenlight generation are all publicly identified.

Strong
1.0

Who pays for infrastructure

Meta says it will pay the full costs of its energy use and fund new and upgraded infrastructure, plus about CA$60 million of local road and water work.

Promising
1.0

Public disclosure so far

Scale, investment, cooling design, partners, jobs and reporting commitments are public. That is materially better than many proposals.

Strong
0.5

Whole-project water

The server cooling story is good. The power plant still needs a complete, current water balance, source, drought plan and zero-potable-industrial commitment.

Half point
0.5

Noise at receptors

Noise can be engineered down. We want the model, tonal and low-frequency analysis, post-startup measurements and a fix-it obligation at the nearest receptors.

Half point
0.5

Emissions & CCS

Greenlight is gas-fired. Alberta's project listing refers to CCS, while current Greenlight public material does not yet give a binding installed-capture specification.

Half point
0.5

Alberta benefit

Investment, construction jobs, permanent jobs and local infrastructure are real benefits. Long-term tax, procurement, compute access and broader Alberta value should be measured, not assumed.

Half point
0.5

Closure & reclamation security

Greenlight now has binding AUC reclamation-security conditions for the dedicated power plant, backed by a third-party estimate of about CA$30.54 million in 2025 dollars. Security starts in year five and reaches the full updated reclamation amount by year 20. We have not found equivalent secured reclamation funding for Meta's data-centre campus.

Half point
What gets Meta to 10? Close the remaining gaps with binding requirements, public measurements and financial security. This is a project with enough money and engineering talent to do all of that.
Meta rendering of the planned Sturgeon County data centre campus
Meta's rendering of the planned Sturgeon Data Centre. Rendering, not an as-built photograph. Source: Meta.

The project in one minute

Big, real and unusually well defined

1 GWMeta announced data-centre scale
CA$13B+Meta announced investment
~3,000construction workers at peak
300+operational jobs

Meta says it will also invest about CA$60 million in local roads and water infrastructure and will report the site's water withdrawals and energy use annually once operational.

Power scale

What does one gigawatt actually look like?

West Edmonton Mall gives Edmonton a useful reference point. Natural Resources Canada reported post-retrofit WEM electricity use of 462,437 GJ per year, about 14.7 MW average. A continuously loaded 1 GW campus is about 68 times that average load.

The WEM number is a historical annual-average electricity figure. The Greenlight and Meta numbers are project capacity/load figures, so this is a scale comparison, not a claim that all facilities run at nameplate output every hour.

The project is enormous. That is a reason to require excellent engineering and accounting, not a reason to assume the engineering cannot work.

Power plan

There is a real supply plan, but it has phases

Now

AESO connection

The AESO allocated 970 MW of its 1,200 MW interim large-load limit to the GLDC load project.

H2 2028

Capital Power

A greater-than-10-year agreement provides 250 MW of capacity and energy in support of Meta's Sturgeon County load.

H2 2030

Greenlight stage 1

Pembina, MSIP and Kineticor reached FID on a dedicated 932 MW gas-fired combined-cycle plant.

2031

Approved expansion envelope

The AUC approval covers up to 1,864 MW in two stages on a 98-hectare site.

What earns the power point

The companies and regulators have identified a credible chain from grid connection to contracted supply to dedicated generation. Meta also says it will pay the full costs of its energy use and new/upgraded infrastructure.

What we still watch

Who pays every attributable grid cost, how the load ramps before Greenlight is online, what happens during outages and maintenance, and whether clean-energy matching is described separately from the physical generation source.

Water stewardship

Count the whole project, not just the server building

1

Data halls

Closed-loop liquid cooling with dry coolers.

Meta says no operational cooling-water use.
→
2

Electricity

Servers turn electrical energy into heat.

The power has its own water footprint.
→
3

Greenlight

Combined-cycle gas plant with air-cooled condensers.

The June 2026 AUC decision gives a current project estimate of 538,000 m³/year.
~1.47Mlitres/day annual-average equivalent for the approved Greenlight project
538Mlitres/year current AUC project estimate
0potable litres/day our standard allows for industrial operation

Our 10/10 water standard

“No potable water for data-centre cooling, power generation, process water or other industrial uses. If the project cannot operate on dry cooling, reclaimed wastewater or another non-potable source, don't build it there.”

Use the right water

The AUC decision describes Greenlight's source as municipal water supplied by Sturgeon County through a new pipeline. It does not establish that the supply will be entirely non-potable industrial process water. For a 10/10 score, the actual source and treatment should be explicit, industrial use should be non-potable, and a multi-year drought case should be published.

Give water back

If reclaimed water is required, the project should fund enough wastewater-treatment or restoration capacity that the useful water returned exceeds the whole campus's consumptive use.

Don't tell us the data centre uses no water while the power plant next door uses water. Count the whole project.

Noise stewardship

Noisy equipment does not require noisy neighbours

Fans, pumps, transformers, generators and heat-rejection equipment can be loud at the source. The engineering question is what reaches the nearest receptor after distance, building orientation, barriers, enclosures, fan selection and operating controls do their job.

AUC Rule 012 requires noise impact assessment for regulated facilities and sets the framework for permissible sound levels and complaints. Our standard goes one step further: publish the receptor model and then publish the measurements after startup.

“A properly designed data centre should be acoustically unobtrusive outside its property. If neighbours can clearly hear it, that is an engineering, siting or mitigation problem, not an unavoidable characteristic of data centres.”
“Noise is a real impact, so design it out, measure it at the receptor, monitor it after construction, and make the project pay to fix it if it gets it wrong.”

Dedicated generation

Greenlight is part of the campus stewardship story

The current FID is for a 932 MW gas-fired combined-cycle plant. The AUC approval allows up to 1,864 MW. Greenlight will capture gas-turbine exhaust heat to make steam and produce additional electricity.

The environmental accounting cannot stop at the data-centre fence. Fuel, CO₂, water, noise and eventual decommissioning at the dedicated power plant belong in the same stewardship picture.

CCS: promising words, incomplete public specification

Alberta's Major Projects listing says Greenlight will integrate carbon capture and sequestration. Greenlight's current public project page and July 2026 FID release describe combined-cycle generation but do not provide an installed capture rate, commissioning date, transport/storage route or tonnes captured. That is why this remains a half point.

Greenlight Electricity Centre project location rendering or basemap
Greenlight project image from the project website. Source: Greenlight Electricity Centre.

Proper stewardship

If the project causes the cost, the project pays the cost

Generation

Project

Dedicated Greenlight plant and its fuel/operating costs.

Grid connection

Project

Substations, connection studies and attributable upgrades.

Water treatment

Project

Non-potable supply, treatment, reuse and drought resilience.

Noise mitigation

Project

Barriers, enclosures, equipment changes and monitoring.

Roads & local services

Project

Incremental infrastructure created by construction and operation.

Cleanup

Secured project funds

Not a promise from whoever happens to own the asset decades later.

The principle: Use Alberta's resources, but pay the full cost of using them. If a project only works by pushing its attributable costs onto taxpayers, ratepayers or a future owner, those are not the project's true economics.

End of life

The cleanup obligation may outlive today's owner

Greenlight now has something important that was missing from our earlier review: binding AUC reclamation-security conditions for the power plant. The record includes a third-party Class 5 demolition and reclamation estimate of approximately CA$30.54 million in 2025 dollars.

Beginning on the fifth anniversary of commercial operation, Greenlight must provide security through irrevocable standby letters of credit, with updated confirmations every five years. The full updated reclamation amount must be secured by year 20 and maintained until a reclamation certificate is issued.

A 10/10 project should still secure the entire campus liability early enough that cleanup never depends on the financial health of whoever owns the assets decades from now.

Living accountability

Promised → Actual

This section should get more useful after the campus opens. The promise column stays. The actual column gets filled with measured annual results.

MeasurePromised / current public positionWhat we want publishedActual
Data-centre power1 GW announced scaleAnnual MWh, peak MW, load factorAfter opening
Potable industrial waterNo 10/10 commitment foundLitres: target should be zeroAfter opening
Data-centre cooling waterNo operational cooling-water use claimedAnnual cooling-loop makeup and maintenance lossesAfter opening
Greenlight source water538,000 m³/year current AUC project estimate (~538M L/year; ~1.47M L/day annual average)Withdrawal, consumption, potable/non-potable source, reuse, discharge and stage-specific useAfter opening
CO₂Gas-fired combined-cycle generationGross emitted, captured, residual, capture rateAfter opening
NoiseMust meet applicable requirementsMeasured dBA plus tonal/low-frequency results at receptorsAfter opening
Infrastructure~CA$60M local roads/water plus energy infrastructure funded by MetaActual project-funded capital and any public contributionDuring build
Jobs~3,000 construction; 300+ operationalPeak construction, ongoing FTE, Alberta/local shareDuring/after build
Taxes / public revenueEconomic benefit claimedProperty tax, corporate tax where reportable, local feesAfter opening
Cleanup securityGreenlight power plant: binding AUC letter-of-credit conditions; full updated amount required by year 20. Equivalent Meta campus security not found.Instrument, amount, beneficiary and update schedule for the entire data-centre campus as well as GreenlightBefore operation / as required

The opportunity

Meta can make this a 10.

There is no reason a CA$13-billion project in a purpose-built industrial area cannot be quiet at its receptors, use zero potable water for industrial operation, pay its infrastructure costs, control and account for emissions, publish the measurements and secure its eventual cleanup.

It can be done right. It must be done right.

Sources and notes

This page deliberately separates company claims, regulator approvals and our stewardship requirements. A corporate promise is evidence of a promise, not proof of future performance.

Scoring note: The 7.5/10 stewardship score is DataCentreDebate.ca's assessment of the current public record. It is not an official government or regulatory score. The score can improve or decline as binding commitments and measured results change.